Refurbishment to Sennheisser Industrial Unit, Tullamore, Co. Offaly

sennheiser11

Description

Renovation to existing factory including provision of new 4 hour fire wall to divide the factory in two. The project included complete separation of existing industrial unit with fire wall. Access for plant and machinery was provided by motorized fire rates roller doors along the length of the building. The project included revised M and E works together with new wall, floor and ceiling finishes. The project was complete during a planned shutdown of the plant which included 24 hour work for a two week period to complete the works on programme.