Stanhope Green

Description

The project consisted of refurbishment to 61 Nr apartments which were split into 4 phases.
This was a live environment working with the client in completing phases within a timeframe to hand over to tenants prior to the next phase commencing. Careful consideration and planning was used for management of both the construction personnel & building tenants, staff etc..

Phase One

This initial phase entailed refurbishment to 25 Nr apartments, corridors, meeting room and stairwells all split into 2 Nr Blocks.
Refurbishment works included for complete new mechanical and electrical installation, floor, wall, ceilings finishes, doors &
windows. Also the courtyard between the 2 blocks received a new paving arrangement, landscaped areas and pedestrian railing. The occupants of this phase were temporally
relocated in Block C whilst these works were being carried out. Upon completion of this
phase all tenants were relocated back to these Blocks A & B.

Phase Three

This phase entailed refurbishment to 12 Nr apartments, corridors, stairwells all located on the first floor of Block C. Refurbishment
works included for complete new mechanical and electrical installation, floor, wall, ceilings finishes, doors & windows refurbishment.
The occupants of this phase were temporally relocated in the remaining phases whilst these works were being carried out. Upon completion of this phase all tenants were
relocated back to the first floor.

Phase Two

This phase entailed refurbishment to 12 Nr apartments, corridors, meeting rooms, canteen all located on the ground floor of
Block C. Refurbishment works included for complete new mechanical and electrical
installation, floor, wall, ceilings finishes, doors & windows refurbishment. There was also a
main heating & distribution room located on the first floor linking back to the boiler room as part of phase 1. The occupants of this phase
were temporally relocated in the remaining phases whilst these works were being carried out. Upon completion of this phase all tenants
were relocated back to the ground floor.

Phase Four

This final phase entailed refurbishment to 12 Nr apartments, corridors, stairwells all located
on the first floor of Block C. Refurbishment works included for complete new mechanical and electrical installation, floor, wall, ceilings
finishes, doors & windows refurbishment. The occupants of this phase were temporally relocated in the remaining phases whilst these works were being carried out. Upon
completion of this phase all tenants were relocated back to the first floor. As part of the final phase there was also repairs and making good to the building envelope roofing & brickworks.